Key Points

The bigger a kitchen's scope, the longer it takes, like a Fairfax kitchen that grew into a whole-home remodel taking 6 months.
Changes along the way can add months, as on a Vienna sunroom addition that took 9 months instead of the 6 that were planned.
A job can pause while finishes are finalized, and inspections can also hold up a job.

You’re planning a remodel in Northern Virginia, and before you sign anything, you want to know how long it will take.

You’ll learn:

  • How long kitchens, basements, bathrooms, additions, and whole-home remodels take
  • How the scope of a project changes the timeline
  • How changes along the way can add months
  • What can pause a job
  • What we do to keep a job on track

How Long Should I Plan for My Kind of Project?

Every kind of remodel has its own average range, though some jobs run longer than that range. Here’s how long each one takes with us:

  • Hall bathrooms: 4 to 5 weeks
  • Bathrooms: 8 to 10 weeks, though some take longer
  • Kitchens: 10 to 20 weeks, depending on the scope. 90% of our kitchens take more than 12 weeks
  • Basements: 12 to 16 weeks, though some take 6 months or longer. Our basements average roughly 16 weeks
  • Additions: 4 to 6 months, though some take a year
  • Whole-home remodels: longer than 5 months, though some take up to a year

Does a Bigger Scope Make a Remodel Take Longer?

How long a kitchen takes depends on its scope, and many of the kitchens we get involve more than the kitchen. They turn into work on part, or all, of the main floor, with the kitchen moved or the floor’s flow changed.

Kitchen with wood cabinets, a white island, and brass pendant lights

Our whole-home remodel in Fairfax started as a kitchen remodel. It grew into the entire main floor, then new flooring on the first and second levels, a larger master bathroom, and remodels of the hall and basement bathrooms. The whole project took 6 months.

White kitchen with a quartz waterfall island and gold ring pendants

Our whole-home remodel in Arlington went further. Inside, we ended up only keeping the shell of the house, causing the remodel to take 1 year.


Can Changes Along the Way Add Months?

Accordion doors open into a sunroom with a dining table

Yes. Our sunroom addition in Vienna is a 250-square-foot sunroom with a stacked stone fireplace, accordion doors, and a 180-square-foot open deck. The homeowners decided on changes along the way, making the project take 9 months instead of the planned 6.


What Can Pause a Remodel Once Work Starts?

Finish selections that aren’t final can pause a job, and so can work that has to be planned before it can be done. Inspections can also hold up a job.

Basement bathroom with a brick wall, a glass shower, and a wood vanity

Our basement remodel in Alexandria ended with a speakeasy-style theater, a large home gym, and a full bathroom with a brick wall. Partway through, the job paused because the finishes weren’t finalized. It also paused while we planned the wiring, because unlike drywall, once you poke a hole in the brick, you can’t take it back.


How Do You Keep a Remodel on Track?

We have you finalize your selections before you sign so the job moves to construction with the schedule, selections, and milestones confirmed.

On one job, work paused for 6 weeks because the finishes weren’t finalized and some structural questions were still open. On another, a 6-month sunroom took 9 because the homeowners kept changing items.

Once work starts, we don’t want any job to stop, because we don’t want any dead days. About 90% of the work is done by our own employees, so there are no subcontractor time slots to wait on. Our field contractor schedules every crew member and moves them between jobs as the work calls for it. Our plumber might rough in one day and move to another job while our electricians come in.

Every job site has a work ticket with your selections, the scope of work, and the as-built layout and plan. Everyone can check it to know exactly what to do and when.

Your project developer runs the job and is your one point of contact. We update the daily log in your project portal 3 to 5 times a week, and we check in with you every 2 to 3 weeks to ask if anything’s bothering you.


Ready to Plan Your Remodel With WISA Design Build Remodel?

If you want to know where your project would land, fill out our contact form or give us a call, and we’d be glad to talk it through. You can also read what it feels like to remodel with us first.

Frequently Asked Questions

How long does a kitchen remodel take?

A kitchen with us takes 10 to 20 weeks, with 90% of our kitchens taking more than 12 weeks. Where yours lands depends on the scope, such as whether the kitchen moves or the work reaches into more of the main floor, as many of our kitchens do.

How long does a basement remodel take?

Our basements take 12 to 16 weeks, with an average of roughly 16. Some run 6 months or longer, so the range for a basement is wide.

What can make my remodel take longer than planned?

A bigger scope, changes along the way, finish selections that aren't final, and waiting on inspections can all add time. We keep a job moving with our own crews and a work ticket on every job site, and you always have one project developer to ask.